Summary

The site preparation, construction and operation of a Deep Geologic Repository (DGR) is proposed for the disposal of low- and intermediate-level radioactive wastes on the Bruce Site in Tiverton. The DGR will also hold waste produced from the continued operation of the Bruce, Pickering and Darlington nuclear generating stations.

Latest News

Note: The following are highlights only. For a complete list of documents related to the Joint Review Panel for this project, please consult the Canadian Environmental Assessment Registry, reference number 06-05-17520.

Licensing Progress Details

(Timelines are best estimates and are subject to change)

Environmental Assessment and Site Preparation

Project Milestone Responsibility
and Status
Date Comment
CNSC and other Federal Authorities Applicant

OPG submits a letter of intent to apply for a Licence to Prepare Site and Construct with a DGR project description (PDF) - in English only

Read Application for Licence to Prepare Site and Construct (August 2007) (PDF) - in English only

Completed
Completed by Ontario Power Generation (OPG)

December
2005

Notice of Environmental Assessment (EA) posted

Completed
Completed by
CNSC

January
2006

Federal Minister of Environment refers EA to a Joint Review Panel (JRP)

Completed
Completed by
the Minister of Environment

June
2007

Draft Envrionmental Impact Statement (EIS) Guidelines and JRP Agreeemnt published for comments

Completed
Completed by
the CNSC/CEAA

April
2008

Comment period on draft Environmental Impact Statement Guidelines and JRP Agreement

Read comments

Completed
Completed

April to
June
2008

Opportunity for the public, Aboriginal groups and other stakeholders to review and provide comments.

Final EIS Guidelines and JRP Agreement published

Completed
Completed

January 2009

Finalized by the federal Minister of the Environment, in consultation with the President of CNSC, based on comments received.

Major Projects Management Office (MPMO) Project Agreement signed (source: CEAA)

Completed
Completed by MPMO

May 2009

An MPMO Project Agreement (source: CEAA) is an agreement between federal Deputy Ministers that outlines the process by which federal departments or agencies will carry out their particular roles or responsibilities during the federal regulatory review of a proposed major resource project. The agreement includes a timeline and schedule for the completion of the regulatory review with regular milestones to allow tracking of progress.

OPG submits EIS with final documentation for Licence to Prepare Site and Construct to JRP (source: CEAA Web site)

CNSC acknowledges receipt of EIS and licence documentation from OPG (PDF)

Completed
Completed by
OPG

April
2011

Appointment of JRP

Completed
Completed by the Minister of Environment and the Governor in Council

January 24, 2012

Appointed by the Minister of the Environment and the Governor in Council, in consultation with the President of the CNSC.

Panel Orientation Session and Comment Period on Environmental Impact Statement and Licence Application for Deep Geologic Repository Project (Source: CEAA)

Completed
Expected from
JRP

February 3, 2012

Webcast and Transcript of Joint Review Panel Orientation Session (PDF)

For a complete list of documents related to the Joint Review Panel for this project, please consult the Canadian Environmental Assessment Registry, reference number 06-05-17520.

Review of EIS, including public review

Expected from
JRP

TBD

Review period led by JRP, including conformity and technical review of the EIS by JRP, public, Aboriginal groups and other stakeholders, and opportunities for public comments. (6 months, not inclusive of time used by applicant to respond to JRP requests)

Information Request 1:
JRP letter of request for additional information (source: CEAA)

Completed
Completed by
JRP
March 8, 2012 JRP sends a letter to Ontario Power Generation requesting additional information concerning the EIS and complete application for a Licence to Prepare a Site, submitted by Ontario Power Generation in April 2011 (source: OPG)
Ontario Power Generation responds in January to the JRP Information Request 1 of December 2009. (Source: CEAA)   Completed
Completed by
OPG
March 19, 2012 Ontario Power Generation responds to JRP’s Information Request 1, concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation in April 2011 (Source: OPG)

Notice of Public Hearings posted

Expected from JRP

TBD

JRP holds Public Hearings

Expected from
the JRP


TBD

To hear views about the EIS and the application for a Licence to Prepare Site and Construct from the public, Aboriginal groups, OPG and other stakeholders.

JRP submits Report to Federal Government

Expected from
the JRP

TBD

The Report is published and presented by the Minister of the Environment to the Governor in Council.

Federal Government’s Response to Report

Expected from
the Governor in Council

TBD

The Governor in Council responds whether the project may proceed or not.

JRP issues Licence to Prepare Site and Construct

Expected from
the JRP


TBD

If the Governor in Council’s response is that the project may proceed, the JRP could issue Licence to Prepare Site and Construct.

Top

Operation

Project Milestone Responsibility
and Status
Date Comment
CNSC and other Federal Authorities Applicant

OPG applies for a Licence to Operate

Expected from
OPG

2015

CNSC holds Public Hearings

Expected from CNSC

2017

CNSC holds Public Hearings on the OPG Application for a Licence to Operate and decides on the application.